Block laying Paper 2 WASSCE (SC), 2023

Question 5

     

    (a)        Sketch in section, each of the following floor finishes:
           (i)         tongued and grooved flooring board finish;
           (ii)        ceramic tiled flooring finish.
    (b)   (i)     List three factors of production required for setting up a brick making
                         industry.
            (ii)    State two entrepreneurial skills required for operating a building material
                         store.
      (c)        List two methods of testing drain pipes.
               

Observation

 

Most candidates were able to answered question 5 correctly except the aspect of question 5 (a) which were not well answered as most of the candidates were not able to sketch tongued and grooved flooring board finish and ceramic tiled flooring finish correctly. Most of the candidate avoid question 5 but few attended it.
The expected response to question 5 (a) is as given below: