 (a)        List three safety wears that should be  worn when casting lintel on a construction  site
      (b)        State  three preliminary site activities prior to site leveling:
      (c)        Sketch each of the following hand tools:
      (i)        jointer;
      (ii)        steel  square.
Observation
Most candidates were able to:
- List three safety wears that should be worn when casting lintel on a construction site
- Sketch each of the following hand tools:
(i)        jointer;
      (ii)        steel square.
      However, some of the  candidates were unable to state three preliminary site 
      activities prior to site leveling:
The expected response to question 1 (b) is as given below:
(b) Preliminary site activities prior to site leveling:
- Site investigation;
- Soil investigation/soil examination;
- Site clearance (i.e., demolitions, felling of trees, grubbing, removal of debris etc.);
- Provision of access road;
- Topsoil excavation;
- Site layout/organization;
- Provision of space for plant and equipment;
- Provision of space for handling spoil/excavated soil.